delays, extensions of time and the prevention principle

ADYARD ABU DHABI v SDS MARINE SERVICES [2011]

This was a construction case in which the issue was whether a party could cancel certain shipbuilding contracts and reclaim sums it had already paid where there had been a delay in completing the ships.  Amongst other things, the Court addressed in what circumstances the shipbuilder was entitled to an extension of time where the customer had requested changes to the design, particularly given the fact that there was a contractually agreed mechanism for the shipbuilder to request an extension.

facts:

decision:

points to note:

back to archive